ERF


Newhaven

Working with principal contractor Hochtief, Bauer Technologies was awarded the contract to install a circular shaped diaphragm wall and foundation barrettes for the energy recovery facility in Newhaven, a process that took considerable time and involved a close working relationship between Bauer and Hochtief.

 

The diaphragm wall and barrettes were completed 3 weeks ahead of schedule, bringing Hochtief’s overall construction scheme back on track after a delay at commencement of the project.

To read the project case study click here