Tel +44 (0)1279 653108

Company Profile

BAUER Technologies is the UK contracting arm of the BAUER Group. We perform deep foundation works on major projects in the UK. We specialise in the design and installation of large diameter piles, diaphragm walls, under-ream piles, plunged column piles and in-situ piled retaining walls.

The BAUER name is synonymous the world over, with the highest standards in foundation engineering. By concentrating on our core competencies we are able to ensure we maintain these high standards in the UK. We specialise in major projects, value in excess of £500K, and technically complex projects.

All our piling and diaphragm walling equipment is manufactured by BAUER. This equipment is particularly suited to dealing with hard strata, including the removal of reinforced concrete obstructions where these obstruct the position of a proposed foundation.

As a wholly owned subsidiary of the BAUER Group we are fully supported by the technical departments of our parent company BAUER Spezialtiefbau (BST) in Germany, allowing access to additional rigs and specialist resources as well as enabling us to benefit from the latest improvements from BST's Research and Development department. By maintaining close links with our worldwide network we are able to draw upon the full depth of BST's experience and engineering knowledge to develop the most innovative and costeffective solution to our client's foundation problems.

Core Competencies

  • Large Diameter Rotary Bored Piling
  • Secant Pile Walling
  • Diaphragm Walling
  • Geothermal Piling
  • Underream Piling
  • CFA Piling

BAUER Techniques

  • Ground Anchors
  • Ductile Piles
  • Mixed in Place
  • Jet Grouting


bored piles



1. Palm Paper Project, Kings Lynn
BAUER Technologies performed the contract for the piled foundations of Europe's largest paper machine. The scope of the project was to install a secant pile wall (hard/hard) and foundation piles to support the machine hall area to a design developed by BHM INGENIEURE Engineering & Consulting GmbH. The final value of the works performed by BAUER amounted to £4.4 million.

2. Waste to Energy Facility, Newhaven
BAUER Technologies executed a diaphragm wall and foundation barrettes to a circular shaft for the facility in Newhaven for Hochtief UK. Different options and alternative technical solutions were proposed and offered during the tendering phase before Hochtief, in joint venture with vonRoll (Switzerland), awarded the project to BAUER Technologies Ltd.

3. Severn Power CCGT, Newport
BAUER Technologies were awarded the £15 million contract for the piled foundations of the new Uskmouth Power Station which consists of two power generating units, each a variety of structures covering an area of 60,000sqm. The scope of the piling contract involved the construction of the piling platform, a preliminary pile testing regime, the erection of an on-site concrete batching plant, the installation of the piled foundations, comprising 439nr 620mm diameter bored piles, 426nr 880mm diameter bored piles and 711nr driven cast iron ductile piles.

4. Pembroke Power Station, Pembroke
BAUER Technologies completed the £5 million contract for the installation of the piled foundations at Pembroke CCGT. Each unit consisted of a variety of sub-structures covering a total area of 40,000sqm. The scope of the piling contract comprised the construction of the piling platform, preliminary trial bores to verify ground conditions and rock head level in the piling area, a preliminary pile testing regime including a fully instrumented test pile, construction of 2,307no. 600mm reinforced CFA piles, 421nr 900mm unreinforced CFA piles and installation of 10nr 1200mm diameter steel liners to 10m depth at the condensate pit, including all associated piling attendances.

5. Pembroke Jetty, Pembroke
BAUER Technologies completed these extremely complex works on a 50 year old jetty on the Severn Estuary at the site of the new 2000MW, Combined Cycle Gas Turbine Power Station, to support the Leibherr LGD 1750 and its 387.5 tonne superlift required for the safe off-loading of five 400- tonne turbines as part of the stations' construction. BAUER chose its rotary system for the job, using thick walled casing with tungsten carbide cutting teeth rotated to toe using BAUER's powerful BG28 rig. For the marine piles, 1220mm diameter casing (19mm thick) was fitted with BAUER spec cutting teeth to ensure penetration through the boulders.

Work was undertaken 24 hours a day, 7 days a week to complete the piling and ensure that the tight deadline was met as the ships in Rotterdam were on equally tight schedules to depart.

6. Tottenham Court Road Station Upgrade, London
BAUER Technologies performed large diameter (2m+) piling down to below 65m deep, diaphragm walling 1m thick x 41m deep, 11nr plunged columns installed into large diameter 48.5m deep piles of diameter 2.4m and various secant pile walls. The project included numerous challenging operations such as;

  • Construction of a 2m diameter bearing pile with permanent liner in a 'D Shape'.
  • Design and installation of a new bespoke plunged column frame 23m long equipped with laser guides which for the first time in the UK bears on naked soil rather than a steel casing clamping the frame in place. The plunge columns are by far the heaviest and longest that the industry has seen for a while with a mixture of 600 x 600 and 700 x 700 columns up to 33m long installed.
  • Installation of a diaphragm wall within a working area of 25m x 30m surrounded by London traffic. Project value £18.9m in JV (BAUER portion £14m). Main Contractor Vinci Bam Nuttall JV. Client London Underground.

7 & 8. Whitechapel and Liverpool Street Stations
BAUER Technologies have been successful in securing two Crossrail Advance Work Stations at Whitechapel and Liverpool Street, for main contractor Bam Nuttall/Kier JV. The contracts consist of Diaphragm Walling, Large Diameter Piling, Pile Removal and Barrettes. Wall thickness reaches a maximum of 1.5m, with depth reaching 60m. Combined contract value £25m.

To print this page or download the company profile document click here.