US Embassy, London

Bauer Technologies was awarded the contract to undertake the piling and diaphragm walling works for the new US Embassy in London. The US Department of State Bureau of Overseas Buildings Operations (OBO), construction contractor, BL Harbert, and prime sub-contractor, Sir Robert McAlpine, selected Bauer Technologies for the early site work package.

The project commenced with preliminary test piling in June 2013, ahead of the main works which started in August 2013. Bauer’s work consisted of the construction of a diaphragm wall; deep, base-grouted, large diameter rotary bored piles; CFA and rotary bored piles. Despite the largescale and complex nature of the project, work was completed to an extremely tight schedule.

US Embassy London

Bauer mobilised a number of rigs to complete the works, including 2no. BG40s; 2no. BG28s; 1no. BG42 and 2no. diaphragm wall grabs.



Client: Bureau of Overseas Buildings Operations (OBO) and BL Harbert
Principle contractor: BL Harbert International
Piling contractor: BAUER Technologies Limited
Contract period: June 2013 to December 2013
Equipment: - 2no. BG40
- 2no. BG28
- 1no. BG42
- 2no. diaphragm wall grabs
Bauer's Scope of Works: - Removal of obstructions using rotary piling equipment
- Installation of guide walls
- Installation of 13,000m2 diaphragm walls and barrettes (two shafts) up to 51m depth